Central Program Health
3 active projects · $301M total BAC
Projects by Attention Score
Ranked by urgency — click to view Project Health
Henderson Substation
PRJ-001
CPI
0.83
SPI
0.76
P1 Risks
5
Budget
$98M / $145M
Top Issue
Cost escalation — CO pipeline $7M pending
Pryor Creek New Build
PRJ-002
CPI
0.87
SPI
0.79
P1 Risks
4
Budget
$52M / $89M
Top Issue
Schedule pressure — 3 milestones at risk
Council Bluffs Phase 4
PRJ-003
CPI
1.01
SPI
0.97
P1 Risks
1
Budget
$41M / $67M
Top Issue
RFI backlog — 4 open, oldest 8 days
This Week's Focus
Prioritized by Bottleneck Detector Agent (A-202)
Resolve Henderson CO-0087
$2.4M blocking substation work
Assign backup Cost Engineer for Central
Single-threaded dependency on Mike R.
Clear Pryor Creek legal review backlog
3 contractor onboardings blocked
Review Dallas Cooling P6 delta
Critical path shifted, SPI slip accelerating
Approve Pryor Creek budget revision
Pending 9 days, blocking commitments
A-202 Analysis: Henderson CO-0087 is the highest leverage item. Resolving it unblocks $2.4M in committed spend and clears 3 downstream dependencies. Estimated portfolio impact: +0.02 CPI if resolved by EOD Thursday.