Portfolio Avg Cycle
6.2d
Across all process types
Onboarding Improved
-36%
Since A-104 deployment (W10)
Top Bottleneck
Legal Review
42% of onboarding cycle time
Total Throughput
247
Processes completed (13w)
Cycle Time Trend
Median days per process type -- 13-week view
Contractor Onboarding
RFI Response
Change Order
Invoice Reconciliation
Permit Application
A-104 Impact: Agent deployed W10. Contractor Onboarding median cycle dropped from 9.2d to 5.2d (-43%). Auto-doc-chase and pre-validation reduced Legal Review wait from 6.1d to 3.2d.
Stage Bottleneck Analysis
Contractor Onboarding -- % of total cycle time per stage
42%
24%
14%
Legal Review42% -- 4.4d
Background Check24% -- 2.5d
Badge/Site Access14% -- 1.5d
Insurance10% -- 1d
Other10% -- 1d